Hume Dam Upgrade

Location: 16km east of Albury-Wodonga on the River Murray
Cost: $60 million
Funding: The Murray Darling Basin Authority
Start date: March 2010
Expected completion: 2015
Description: Installation of an improved filter and drainage system on the junction between the concrete spillway and southern embankment; construction of a concrete buttress on the southern training wall and possible spillway modifications to improve the capacity of the dam to manage extreme floods. 

Benefits

  • Improved dam safety in the event of extreme flooding and earthquakes
  • Dam upgraded in line with contemporary best practice
  • Economic flow on to local community

Milestones

  • Filter Drainage - Southern Junction - March 2010
  • Strengthening Southern Training Wall - 2011
  • Additional Flood Capacity - Upgrade - 2012

Updates

  • Filter drainage on track - Construction contract let to Advanced Foundation Solutions Pty Ltd ($10m) and the construction management contract let to SMEC.
  • Strengthening Southern Training Wall - Detailed design contract let to URS Australia January 2010. Shortlist construction contractors via expression of interest process will commence mid 2010
  • Additional flood capacity - Hydrology investigation completed December 2010

Fact Sheet

 Hume Dam fact sheet

Contact

Project Manager: Phil Farnik
Contact Details: (02) 9354 1002