Wyangala upgrade
Location: Lachlan River, 50 km upstream of Cowra
Dam completed: 1935 (enlarged 1971)
Storage capacity: 1,220,000 megalitres
Upgrade construction cost: $43 million
Funding: The NSW State Government
Start date: 2009
Expected completion: 2014
Stage one:
1A - Spillway radial gate raising and locking.
1B - Downstream spillway chute wall raising.
1C - Parapet wall crest raising.
Storage capacity and normal water releases will not
be affected by the upgrade.
Benefits
- Improve capability of the dam to withstand extreme floods
- Improve environmental performance
- Increase sustainable regional development
- Stimulating local economy during construction phase
- Bring dam into line with contemporary security practices
Project timeline
1A Spillway radial gate raising and locking (work package)
- Late 2011 award construction contract
- Early 2012 commence construction
- Late 2012 construction complete
1B Downstream spillway chute wall raising (work package)
-
Late 2009 award construction contract
-
Late 2009 commence construction
-
July 2010 complete construction
1C Parapet wall crest raising (work package)
-
Mid 2013 award construction contract
-
Mid 2013 commence construction
-
Late 2014 complete construction
Updates
-
March 2009 - Proposed to restrict public vehicle access to the road atop the dam wall during construction and beyond for safety of staff and to better protect critical dam infrastructure
- June 2009 - Consultation undertaken with local community including Cowra and Boorowa Council to decide on an alternative access route to Wyangala village. 35 face-to-face interviews were conducted with up to 50 local residents to discuss the impact of various options relating to the road closure
- July 2009 - NSW Minister for Water Phillip Costa ordered an independent review to determine a suitable alternative access and rule out the Mt McDonald Road option
- February 2010 - Commenced construction on chute wall raising works
- July 2010 - Completed construction on chute wall raising works
- August 2010 - Wyangala Working Party endorsed option to build a new road and bridge to connect Darby's Falls Road and Trout Farm Road
- December 2010 - Contract awarded for detailed design of bridge and road access
- January 2011 - Contract awarded for detailed design of gate raising and locking system
- March 2011 - Commence review of environmental factors (REF) into the alternative access and additional community consultation
- October 2011 - Complete REF into the alternative access
- November 2011 - Alternative access REF on public display for three weeks
Review of Environmental Factors Reports
Review of Environmental Factors - Wyangala Dam stage one safety upgrade new road and bridge over the Lachlan River (PDF 27MB)
Information sheets
October 2011 Wyangala information sheet
Media releases
January 2012 2012 Wyangala works to boost local economies
December 2011 Further local input into Wyangala bridge and road
November 2011 Report says Wyangala village to benefit from new access
May 2011 Wyangala consultation continues
April 2011 Proposed Wyangala route on display
December 2010 Wyangala road and bridge design tender awarded
August 2010 New bridge to link community during $31 million upgrade
February 2010 Wyangala upgrade works will not impact road access
March 2009 Wyangala Dam road closure
Contact
Project Manager: Kock Ooi
Contact details: (02) 8245 2007
