Fish River pipeline construction
Location: Between Duckmaloi Water Treatment Plant and Rydal Dam
Project cost: $8 million
Funding: Fish River Water Supply customers
Start date: Mid July 2011
Expected completion: June 2012
Description: Renewal of approximately 3.7 km's of prestressed concrete pipeline with steel pipeline for the Fish River Water Supply Scheme.
Benefits
- Reduce maintenance costs by eliminating breakages
- Saving water by minimising leaks
Milestones
- Detailed concept design - December 2010
- Award construction - April 2011
- Construction to commence - July 2011
- Completion - April 2012
Updates
- Detailed concept design completed - April 2011
- Award construction - April 2011
- Construction commenced - July 2011
- Construction completed - April 2012
Media releases
May 2012 Mountainous terrain overcome to complete pipeline project
January 2012 Fish River Water Supply pipe upgrade on track
June 2011 $8 million Fish River pipe upgrade